On assessment of whether liquidated damages (LD) were payable by a contractor for delays in completion of work, the Delhi High Court (HC) in North Delhi Municipal Corporation v. IJM Corporation Berhad, held that once a request for extension is received and granted, and the contractor completes the work in the contractual and extended periods, LD is not payable. The HC also held that a competent authority cannot, after the extended period, turn around and re-evaluate the extension granted, to the detriment of the contractor.